Five steps. Forty-five days.

From quote request to power-on, here's exactly what happens — and how long each step takes.

Step 01 — Design01
Within 24 hours

Design

Submit your quote. We pull your roof from satellite, run shading and panel layout in Aurora, and email you the design + proposal — typically within 24 hours.

Step 02 — Permit02
1–2 weeks

Permit

Once you sign, we pull permits. In Houston and San Antonio, we use SolarAPP+ for same-day approval where eligible. Statewide, we use Texas SB1202 third-party permitting to avoid AHJ delays.

Step 03 — Install03
1–2 days

Install

Our Texas-licensed crew shows up with everything pre-staged. Most installs complete in a single day — two days max for larger systems or complex roofs. CompanyCam photos at every milestone.

Step 04 — Inspection + PTO04
1–3 weeks

Inspection + PTO

AHJ inspects. Utility approves interconnection. Permission to Operate (PTO) is issued. We monitor every utility process actively — no waiting on hold for you.

Step 05 — Service for life05
From day one

Service for life

Once your system is live, Bodhi monitoring is automatic. Any drop in production, any error — we know first. Your service contract is included for the life of the system.